THE PROJECT:
Telelink Infra, as EPC contractor and battery storage integrator, designed and delivered a hybrid solar power plant for Green Power 21, a Bulgarian solar and battery storage operator. The 2 MWp PV plant is co-located with a 3 MWh / 1.5 MW IPS EXERON X-BESS – a European-made LFP battery energy storage system (BESS), AC-coupled and grid-connected.
THE CHALLENGE:
The plant’s output followed the sun, not the market. Surplus energy was exported at low prices or lost to solar curtailment when grid limits kicked in. Adding storage also meant bidirectional power flows at the medium-voltage grid connection, along with strict grid-code, protection and fire-safety requirements.
THE SOLUTION:
- Engineering & design: site and grid connection assessment, PV + BESS sizing validation, yield and dispatch modelling, protection, safety and grid studies
- EPC: design, procurement, construction, BESS installation and commissioning
- Digital energy management: EMS/SCADA coordinating solar generation, battery dispatch and export limits in real time
- Operations & maintenance: 24/7 monitoring, predictive maintenance and SLA-backed O&M for solar and battery storage
THE RESULT:
A controllable energy asset instead of variable generation. Through energy arbitrage and load shifting, the battery alone is projected to add €25,000–€95,000 in annual value – with room for balancing services and flexibility markets next.